As summer continues to heat up, work on the expansion and renovation of the Luth Athletic Complex has been moving along at a scorching pace. Considerable progress continues to be made on the facility which will be the cornerstone of Holy Cross' athletic success for many years to come.
The new sports performance center is now complete, while work on the indoor center, auxiliary gymnasium, offices, meeting rooms and locker rooms continues to move forward. Several of these areas are approaching completion and will be going on line in the coming months.
Progress will continue to happen quickly, so check back in the coming weeks for our next update!
For more details on the Luth Athletic Complex, click here.
To view our live webcam of the Hart Center construction, click here.
All construction services at the Luth Athletic Complex are being provided by BOND, the Northeast's premier full-service construction management and general contracting company offering coordinated building and self-performing civil & utility services. For more information, visit www.bondbrothers.com.
Check out some of our latest photos and videos on the progress which has been made recently.
July 2017

The new sports performance center.

Wood wall paneling installation in the north lobby.

Metal panel installation at the north elevation of sports performance.

Wood benches and landscaping at the secondary entrance.

Framed tiered seating platform in the team meeting room.

Wood flooring material acclimating to climate in the auxiliary gymnasium.

Wood locker installation in the basketball locker room.
June 2017

The new walkway from the main entry to the secondary entry.

Taping tables in the newly opened sports medicine suite.

Hydrotherapy plunge pools in the sports medicine suite.

Painting of the exposed trusses in the indoor center.

The lobby and grand stairway outside of sports performance.

Flooring installation inside of sports performance.
May 2017

Paver installation on the walkway from the main entry to the secondary entry.

Insulated metal panel installation on the west elevation of the indoor center.

Canopy steel erection at the southeast corner of the indoor center.

Duct installation and drywall taping on the north interior wall of the indoor center.

Duct installation and drywall taping on the west interior wall of the indoor center.

Staging for ceiling and light installation at the secondary entry.

Hydrotherapy pool tile installation in sports medicine.
April 2017

Mechanical, electrical and plumbing rough in at the sports performance stairwell.

Overhead duct being installed at the indoor center, along with drywall installation for the north west walls.

Precast structures for the StormTrap retention system to be installed below grade at the east side of the indoor center.

Insulated metal panel being installed on the east elevation of the indoor center.

Brick pavers being installed at the main entrance.

Metal panel installation outside of the auxiliary gymnasium.

Temporary protection in the football locker room for the overhead piping to the new sports medicine area.
March 2017

Installation of exterior metal panels at the north elevation of the indoor center.

Refueling station and coaches offices in sports performance.

Drywall installation at the west wall of the indoor center.

Curtainwall installation outside of sports performance.

View from the roof of the indoor center storage room.

3D image of the officials' locker room.

3D image of the hydrotherapy room.
Read "An Inside Look At The Luth Athletic Complex".
February 2017

A view of sports performance through the indoor center.

The north elevation of the Luth Athletic Complex.

Structural steel to support the new batting cages in the indoor center.

The secondary entrance, near the northeast corner of the lower level locker rooms.

Windows from the basketball offices into the auxiliary gymnasium.

The new administrative offices.

The new administrative offices.
January 2017

Masonry mixing operation in the interior of the indoor center.
Curtainwall installation at the secondary entry.

Installation of storm drain piping for the indoor center roof gutter.

Scaffolding for the brick installation at the south elevation.

Drywall installation at the entrance to sports performance.

Masonry installation at the upper level restrooms.

Support structure for the exterior cladding at the indoor center.
December 2016

Exterior wall framing and sheathing at east elevation of sports performance.

Installation of insulation and framing for metal wall panel system at north elevation of sports performance.

Installation of curtainwall at north elevation of sports performance.

Placement of concrete slab at auxiliary gymnasium.

Installation of curtainwall at sports performance.
November 2016

The inside of the new auxiliary gym.

The exterior of the new sports performance facility.

Work taking place inside the new indoor center.

The exterior of the new indoor center and the sports performance facility.
October 2016
The new main entrance to the Luth Athletic Complex.

The ice rink is ready for the Crusaders to open the 2016-2017 season.

The Crusaders practicing on the new court in the basketball arena.
Rev. Philip L. Boroughs, S.J. speaking in front of the Luth Athletic Complex on Oct. 25.

The final beam of the steel structure going into place on Oct. 25.
September 2016

The new women's ice hockey locker room.

Installation of steel reinforcing for the concrete roof over sports performance.

Roof trusses at the new indoor center.

Final work being done in the basketball arena.

Masonry wall construction in the lower level of sports performance.

Masonry construction at the East elevation of sports performance.
August 2016

Aerial view of the concrete placement on the roof of sports performance.

The men's ice hockey locker room.

The subfloor inside the basketball arena.

The basketball coaches offices prior to concrete placement.

Locker rooms below sports performance prior to concrete placement.

The future basketball team meeting and film room area.

The women's ice hockey locker room.
July 2016

Installation of the new ceiling in the basketball arena.

Structural steel for the sports performance area.

Structural steel for the team meeting rooms.

Structural steel for the sports performance area and secondary entrance.

Construction progress at the new main entrance.
Framing of the coaches offices for men's ice hockey.
June 2016

New structural steel at the main entrance to the Luth Athletic Complex.

Framing of the new ceiling in the basketball arena.

New structural steel at the main entrance to the Luth Athletic Complex.

Foundation installation at the southeast corner of the new indoor center.

Ramp construction of the ADA platform in the ice hockey rink.

Electrical duct bank installation in the road to the west of the Luth Athletic Complex.

Backfilling operation at the west wall of the new indoor center.
May 2016

Formwork and reinforcement in progress on the northeast corner of the new indoor center.

Waterproofing and backfilling in progress on the southwest corner of the indoor center foundation / retaining wall.

Foundations placed and backfilled for the new main entry area of the Luth Athletic Complex, post demolition.

The new main entry to the Luth Athletic Complex, with the elevator shaft placed and structural steel erection in progress.

Audio / visual trenching in progress at the basketball arena, post demolition.